West Stadium Boulevard detours, public meeting notice and maps

Requested

January 27, 2010

Recieved

January 27, 2010

Posted by

Edward Vielmetti

Date posted

January 27, 2010

Construction Schedule & Detour

Construction is expected to begin March 1 and be complete by November 2010.

One lane of westbound traffic will be maintained on West Stadium Blvd between Pauline and Seventh throughout the construction*. Eastbound traffic will be detoured via Pauline to Maple Road to Scio Church Road to Main Street to West Stadium Blvd. Detour Map (pdf)

*Eastbound access to Suffolk Ave will be permitted.

Due to the University of Michigan’s expected lane closure on Main Street (to complete the football stadium work), construction across Seventh Street will take place in the period between the end of the Art Fair and the beginning of the 2010 school year. This construction will require the temporary closings of Seventh Street alternating between the north side and south side. Associated detours will be placed. Map of Seventh St Detours (pdf)

http://www.a2gov.org/government/publicservices/project_management/upcomingprojects/Pages/WestStadiumReconstruction(SuffolktoHutchins).aspx

Files